Project: Southwark Park Gallery install
Activity: Final Show Risk Assessment
Description: Final dynamic risk assessment of the gallery space to ensure public opening to planned schedule
Hello all. Sorry I will be away next week for the last two days of install at the Southwark Park Gallery Show. We will need to do some final checks to make sure the show can open to the public as planned. These are all the things that need to be done to get us to a ‘safe to open’ stage, in the timescale we have. I’ve written it as a rough method statement, to be followed in order.
Steps in order:
Day 1
- A final check offlagged work: We received and reviewed student written paper risk assessments prior to the install, and flagged certain works as requiring additional attention during install due to complicated install plans or due to yellow or orange residual risks after mitigations were put in place on the written risk assessment. So, firstly, check in with these students and insure that if their mitigations are not yet in place, that they have a plan for them to be in place by the end of today. For these complex installs, we cannot have last minute, untested, mitigations coming in on the final day of install.
- Make note of any works that will need a further inspection tomorrow, for example for an agreed mitigation being missing, and convey to the students that if it is not there by tomorrow AM the work must be withdrawn.
- Do a final check of all work using mains electricity: Visually inspect all cabling used for any work plugged into mains electricity – any nicks or damage to any part of the cabe and is needs to be replaced. Ensure any power adaptors or extension leads that are used have their up-to-date PAT test sticker, or receipt of purchase. We cannot have unverified electoral equipment in the space during public opening. All student electrical equipment should have been PAT tested on the booked dates prior to the install, but over the course of the install equipment may have been swapped out or become damaged so an additional physical inspection is required.
- Again, make a note of any work that needs specific further inspection tomorrow, and convey this to the student.
- Hanging points / suspended work: Inspect all suspended work to make sure it is using it’s pre-agreed hanging points. Students can sometimes add additional hanging points that are not securely rated to the ones in that are already in their plan, for example from electrical ducting in the ceiling. If you are unsure if a hanging point was pre-agreed, you can check with the Gallery team, as they will know the safe working loads of the zones of the install space.
- Again, make a note of any work that needs specific further inspection tomorrow, and convey this to the student.
- Wobble Test / Stage Weights: Inspect any freestanding work that needs to be weighted down, for example isosceles frames or freestanding projections screens. Make sure that any agreed mitigating weights for flagged works are in place, and give any freestanding work a wobble to see how securely it is standing, and not at risk of partially or fully falling. Make sure that any students who’s work needs additional weighting are aware they will need to get weights, either purchased or from the CLS, in order for the work to be shown.
- Wall Fall Test: Inspect any wall mounted work that looks loose – for example hung with command strips on an uneven surface, with an uneven drop hang, or where the nail is not perpendicular to the wall. If any work looks unsafe or unsecured, advise the student on the necessity of a new hanging solution.
- Check in with tutors: Discuss any unresolved issues that have arisen when testing and flagging issues earlier in the day with the student’s relevant tutor. They will know more about the student’s practice, circumstance, temperament etc. and will be able to advise on an approach or assist with enforcing. Each student is different and will respond best to different approaches; their tutor will likely be the quickest way to find out what this best approach is.
- Write And Share A Working At Height List And Order: Share this with the relevant students and tutors and ensure they understand that it is a list of priority, that will be limited by time and human resource.
Day 2
- Final Working At Height: First thing, the final working at height list from yesterday. Do this first so as to allow you to easiest restrict access to the working area. Ensure this doesn’t expand in scope beyond the list, otherwise it will spiral, take all day, and prevent the show form opening.
- Check in with tutors again: Follow up with tutors on yesterday’s check in and if possible make an arrangement to go round each course’s work with the relevant tutors of that course, doing the final sign off of the work.
- Check In On Noted Works From Yesterday: A quick check to make sure any changes requested (new electrics, new mitigations, new mountings etc.) are in place or that the students and/or relevant tutors have a plan in place.
- Access routes: Go round all spaces a tape measure, ensuring minimum 1.2m access routes to all fire escape routes, as this is the legal minimum required. Additionally, ensure wherever possible that there are no cable runs across access routes to fire escapes, as these can cause a trip hazard in an emergency.
- Final Cable Run Checks: Make sure any cable runs that are still in pace are secured in place with cable covers or duct taping done by our team or the gallery team. If you are unsure of what materials can be used to secure cables in a space check with the Gallery team.
- Repeat steps 2 and 3 in turn: Go through each course and check in, then do subsequent loops of the install space until no more work needs checking.
- Sign Off With Gallery Team: Ensure the show looks good to open from the SLG team’s perspective – they are the final arbiters of the space so the final say-so on everything is theirs.
- Congratulate Students: A small but important step. Make sure the students feel proud of their work and their perseverance with the challenges of an offsite install!